Schedule of Required Inspections

New Construction or Additions 

  1. Footing Inspection - when forms are in place
  2. Footing drains
  3. Foundation and coating - before backfilling
  4. Mechanical and framing inspection - must be made before work is covered
    1. Rough framing
    2. Rough electrical
    3. Rough plumbing
  5. Insulation inspection
  6. Final inspection and Certificate of Occupancy (CO) must be obtained before building in occupied

Remodeling 

  1. Mechanical and framing inspection - must be made before work is covered
    1. Rough framing
    2. Rough electrical
    3. Rough plumbing
  2. Insulation inspection

Pools

  1. Footings, grounding, electric/trench, fence and alarms at final inspection

Sheds

  1. Footing
  2. Framing
  3. Electrical (if needed)
  4. Final inspection